Project Intelligence Hub
Time Impact Analysis Report | Director Pack
The Director Pack generator uses the master Word template in:
templates/time_impact_analysis_report_director_pack.docx
Generation workflow:
- Open the existing Streamlit app.
- Go to
Delay TIA -> Download Reports.
- Open the
Report Generator section.
- Complete the required fields:
- Project Name
- Data Date
- Revision
- Review the replacement preview and source status.
- Click
Generate Time Impact Analysis Report | Director Pack.
- Download the generated DOCX.
Current behavior:
- The original DOCX template is copied before any replacement.
- Placeholders and selected table values are updated only.
- Original charts and images are preserved by default.
- Every generated DOCX is logged in the SQLite
generated_outputs table.
Current limitation:
- Embedded charts and images are preserved by default and are not regenerated unless future chart-replacement support is added.
Supported replacement fields:
- Project name
- Contract number
- Data date
- Revision
- Employer / Client
- Contractor
- Contract form / clause basis
- Accepted baseline programme
- Impacted update programme
- Calendar basis
- Schedule file name
- Schedule options
- Longest path / critical path basis
- Retained logic / progress override
- Out-of-sequence progress treatment
- Constraints
- Calendars
- Open ends
- Negative float